The Park District of Oak Park General InformationOn-line BrochureComing & GoingsGive us your Feedback

Barrie Park Update Page

 

Park District of Oak Park Wins Agreement.
Commonwealth Edison Agrees
to Clean-up Deadline.

OAK PARK— (July 8, 1999)—After months of negotiations, the Park District of Oak Park has secured from Commonwealth Edison and Nicor Gas an agreement ensuring that the remediation of Barrie Park will proceed according to the original schedule on January 3, 2000. This timeline should ensure Barrie Park will be cleaned up and environmentally safe by fall of 2000.

"The Park District of Oak Park’s goal has always been to move the process along on terms most favorable to all the neighbors and users of Barrie Park," said David Gullo, President of the Park District Board of Commissioners. "The agreement marks the first-time the utility companies have stipulated in writing their intent to begin the remediation process in the time frame suggested by the Park District of Oak Park."

The negotiations had been over the speed with which the utility companies would complete Phase III of the soil testing and the preparation of the remediation-objectives report. The Park District of Oak Park opposed the unnecessary duplication of testing in Phase III and sought to have the remediation objectives defined by the beginning of September 1999. The Board withstood pressure from the Illinois Environmental Protection Agency over the Board’s decision to deny access for Phase III testing until the utilities committed to the remediation start-up date.

The Park District of Oak Park’s negotiators agreed to issue a new access agreement to the utility companies for Phase III testing with the understanding that the utilities would commit in writing to a timeline that the Park District of Oak Park and its consultants agreed to last November.

"This is a significant achievement for the Park District because now we have a set timeline that will enable us to focus on the remediation objectives report," Gullo said. These were difficult hard fought negotiations but the Board continues to act in the best interests of the neighbors and users of Barrie Park."

The Park District of Oak Park has been monitoring the comprehensive environmental and safety plan at Barrie Park since its inception in November of 1998.

Contact:
Marilyn Katz, Brian Berg
312.822.0505

David Gullo
708.386.9090